| Client and Nature of the Project | Scope of Project |
| Khoemacau Copper Mine | Electrical and Instrumentation for Boseto Process Plant Refurbishment and Expansion |
| Khoemacau Copper Mine | - Supply and Install 11kv O/H line complete with transformers for Zone 5 Underground Project Power reticulation |
| Karowe Mine | - Supply and Install all electrical and mechanical equipment for six new boreholes |
| Orapa Mine – Plant 1 A&I Infrastructure Replacement | - Replacement of Remote I/O panels and support structures - Replacement of old cable racking and re-strapping control cables |
| Orapa Mine – Plant 2 Crusher VSDs Upgrade Project | - Replaced the old 800kw Masterdrive VSDs with the new Synamics Drives |
| Orapa Mine – Electrical Reticulation to 30 new Houses | - Installation of new Feeder Pillars and supply cables to new houses under construction |
| Karowe Mine – Plant Upgrade Projects under DRA Global | - Tailings Conveyor Relocation - Installation of new 11kv RMU - Power reticulation to new Core-Shed - Installation of new Main Gate and PCC infrastructure |
| Orapa Mine – Tailings Minisubs Replacement | - Replacement of old Tailings Minisubs - Replacement of old Tailings feeder 11kv XLPE cable. - Installation of new RMU and all 11kv Terminations |
| Orapa Airport Upgrade – Bulk supply upgrade under Asphalt Botswana | - Installation of 6.6kv XLPE supply cable from Overhead Power Line - Installation of new 6.6kv Minisub and Feeder Pillar - Installation of Tower Lights |
| ADP Projects – New Bulk Sampling Plant at Boteti Mine | - Installed new 1MVa 11kv/400v transformer for the BSP Plant complete with 95mm2 XLPE cable from the O/H Line - Installed and commissioned new 400v MCC complete with all cable runs to drives. - Installed all plant lighting |
| Debswana Orapa Plant No.2 – Cable Racking Refurbishment | - Replacement of rusted and broken cable ladders with new ones |
| DRA – Karowe Mine Expansion Plant Upgrade | - Installation of 11kv Mini-substations including 11kv XLPE cable terminations and splicing. - Replacement of 100kva Pole mounted transformer with a ground mounted 315kva Mini-substation - EQSTRA/MOOLMANS mining contractor laydown area 11kv power line construction and all site reticulation works |
| Sedgman Australia – Boseto Mine Construction - Maun | - Installation of containerized 13 panel 11kv switch room complete with all cable terminations - Installation of 11kv cable reticulation networks to plant transformers complete with terminations and splices - Installation of 25m Scissors type lighting towers for the plant |